Hydrotherapy Pool Refurbishment
St Luke's Care Hospital

Scope of Works

In October 2019 Aurify Constructions commenced the refurbishment of St
Luke’s Care Hospitals hydrotherapy pool.

The works involved the demolition of existing bathroom amenities within the
hydrotherapy pool which took place during hospital operating hours. Aurify
successfully contained the demolition and construction works from the
operating hydrotherapy pool and hospital.

The project continued over the hospital’s Christmas shutdown period,
allowing Aurify to commence demolition of the pool tiles, surrounding
concourse tiles, office and shower facilities. New mechanical platform and
plant was installed on the roof above, in conjunction with newly installed
structural steel to the bathroom facilities below.

In the demolition stage of the project, Aurify identified a cost saving for the
client through a redesign of the original scope allowing for a give back in
costs.

The Hospital operates a sleep centre which conducts regular sleep tests.
Aurify successfully coordinated noisy construction activities with the client to
ensure there were no zero disruptions to hospital operations.